Village of Hubbardston
Main Street Reconstruction
878390
Design Review Meeting Minutes
Meeting Held: August 17, 2026 at 9:00 a.m.
Items Discussed:
1. Introductions
- Attendees: Paula Peiffer, Phil Schneider, Doug LaVoie, George Nevills, Rick Thorne, Peter Tierney, Danell Diakow
2. Project Scope & Objectives
The proposed project consists of the following:
- Crush and Shape Main Street from Washington Street to Cook Road
- Sidewalk ramp replacement at Hanover and Church Street
- Discussed and agreed to add sidewalk ramp replacement at Howard Ally as well.
- Minor drainage improvements including ditch cleanout
- Discuss areas of drainage concerns
- Ditch cleanout needed south of drive to 6800.
- Drainage concerns at 440 E. Main St. Review slope of road and getting water to culvert vs. towards home.
- Discuss areas of drainage concerns
- Guardrail replacement
- Include existing guardrail replacement.
- Look at adding additional guardrail at culvert south of drive to 6800.
- Detour route
- NE Route: Cook, Jones, to Island Rd or Maple Rapids Rd.
- Village would like to keep Maple Main St between Island and Washington accessible as much as possible. F&V to review sequencing if possible without adding excessive costs.
- SW Route: Stoudt to Cowman
- NE Route: Cook, Jones, to Island Rd or Maple Rapids Rd.
- Overview of bidding process
- Project will be publicly bid out; on F&V’s website, contractor bid rooms, Village’s website (if desired), and directly contacting local contractors.
- Bid opening will happen at the Village at date and time specified in contract documents.
3. Progress to Date:
- Survey has been completed.
- Soil borings have been obtained.
- Preliminary plan set and specifications drafted.
4. Project Schedule
- Client Review Meeting: August 17, 2026
- Survey Field Work: Complete
- Geotechnical Work: Complete
- Prepare final plans, specifications, and cost estimate: August-October 2026
- Submit final documents to Village for Review: October 2026
- Issue for Bids: November 2026
- Receive Bids: December 2026
- Bids holding period will need to be long for Village to award project after receiving MDOT funds.
- Bids present to Board: December 15, 2026
- Project can be awarded contigent on receiving MDOT funds.
- Anticipated to Receive Construction Funds from MDOT: January/ February 2027
- Construction: Spring/Summer 2027(approx. 6 weeks)
- Contractor to be done with project a week before Memorial Day or project to wait until after.
5. Permitting
- Ionia County SESC permit (contractor to obtain)
- County Road permit for Detour Route (Ionia and Clinton County)
6. Open Discussion
- Put back driveways to match existing material.
- Add detail to put in HMA shoulder at gravel drive locations.
- Provide cost to upgrade gravel to HMA for Village to evaluate option.
- Replace road approaches on Island Road.
- Village wants to keep any millings from project. Village to let F&V know where they want them stockpiled to include in project documents.